Section 80.80.070. Consumer-owned utilities—Baseload electric generation—Long-term financial commitments.  


Latest version.
  • (1) No consumer-owned utility may enter into a long-term financial commitment unless the baseload electric generation supplied under such a long-term financial commitment complies with the greenhouse gas emissions performance standard established under RCW 80.80.040.
    (2) The governing board shall review and make a determination on any long-term financial commitment by the utility, pursuant to this chapter and after consultation with the department, to determine whether the baseload electric generation to be supplied under that long-term financial commitment complies with the greenhouse gas emissions performance standard established under RCW 80.80.040. No consumer-owned utility may enter into a long-term financial commitment unless the baseload electric generation to be supplied under that long-term financial commitment complies with the greenhouse gas emissions performance standard established under RCW 80.80.040.
    (3) In confirming that a long-term financial commitment is for baseload electric generation, the governing board shall consider the design of the power plant and the intended use of the power plant based upon the electricity purchase contract, if any, permits necessary for the operation of the power plant, and any other matter the governing board determines is relevant under the circumstances.
    (4) The governing board may provide a case-by-case exemption from the greenhouse gas emissions performance standard to address: (a) Unanticipated electric system reliability needs; or (b) catastrophic events or threat of significant financial harm that may arise from unforeseen circumstances.
    (5) The governing board shall apply the procedures adopted by the department to verify the emissions of greenhouse gases from baseload electric generation under RCW 80.80.040, and may request assistance from the department in doing so.
    (6) For consumer-owned utilities, the auditor is responsible for auditing compliance with this chapter and rules adopted under this chapter that apply to those utilities and the attorney general is responsible for enforcing that compliance.
    (7) This section does not apply to long-term financial commitments for the purchase of coal transition power with termination dates consistent with the applicable dates in RCW 80.80.040(3)(c).
    NOTES:
    FindingsPurpose2011 c 180: See note following RCW 80.80.010.